498056 / ST CLAIR POWER PLANT BOTTOM ASH BASINS
4901 POINTE DRIVE, EAST CHINA, MI 48054

QMR Reports (6)

Due Date
Date Received
1/30/2024 1/30/2024
Due Date:
1/30/2024
Date Received:
1/30/2024
Responsible Person:
Darling, Aaron
Statistical Exceedence?:
No
Branch:
WA - Warren District Office
Review Notes:
- Statistical evaluation for the initial sampling event resulted in
exceedances for chloride at MW-16-01 and pH at MW-16-02. - Verificat
on resampling results for chloride at MW-16-01 and pH at MW-16-0
were below respective prediction limits.
7/30/2023 7/28/2023
Due Date:
7/30/2023
Date Received:
7/28/2023
Responsible Person:
Darling, Aaron
Statistical Exceedence?:
No
Branch:
WA - Warren District Office
Review Notes:
- Statistical evaluation for the initial sampling event resulted in
an exceedance of Total Dissolved Solids (TDS) at MW-16-03. -Verificat
on resampling result for TDS at MW-16-03 was below the prediction limit.
1/30/2023 1/30/2023
Due Date:
1/30/2023
Date Received:
1/30/2023
Responsible Person:
Darling, Aaron
Statistical Exceedence?:
No
Branch:
WA - Warren District Office
Review Notes:
-Statistical evaluation for the initial sampling event resulted in
exceedances for chloride @ MW-16-01, MW-16-02, MW-16-03, MW-16-04 -Verificat
on resampling results for chloride @ MW-16-01, MW-16-02, MW-16-03, MW
16-04 were below respective prediction limits.
7/30/2022 7/29/2022
Due Date:
7/30/2022
Date Received:
7/29/2022
Responsible Person:
Carnagie, Mary
Statistical Exceedence?:
No
Branch:
WA - Warren District Office
Review Notes:
1/30/2022 1/31/2022
Due Date:
1/30/2022
Date Received:
1/31/2022
Responsible Person:
Carnagie, Mary
Statistical Exceedence?:
No
Branch:
WA - Warren District Office
Review Notes:
7/30/2021 7/30/2021
Due Date:
7/30/2021
Date Received:
7/30/2021
Responsible Person:
Carnagie, Mary
Statistical Exceedence?:
No
Branch:
WA - Warren District Office
Review Notes:
New Row
Due Date:
Date Received:
Responsible Person:
Statistical Exceedence?:
Branch:
Review Notes: